Made for Federal Contractors
Confirm Direction Without Accepting Scope
Also useful for: people in Government
Document ambiguous government direction while protecting the contract position, requesting authorized confirmation, and keeping the working relationship constructive.
Create a free account to save your progress and use this Playbook.
Use this when
A government contact gives verbal, informal, or unclear direction that may change scope, schedule, cost, staffing, priorities, acceptance criteria, or performance risk.
You'll need
- Contract context
- Direction received
- Direction source
- Direction channel
- Possible contract impact
- Current work posture
- Operational urgency
- Desired response and reviewers
You'll get
- The direction separated into facts, assumptions, and open questions
- The source's authority identified or marked for confirmation
- Every plausible contract impact classified as confirmed or potential
- An interim work posture selected
- A neutral confirmation email reviewed for accidental acceptance
- A clear request for authorized written direction included
By the end of this playbook
You will have:
- The direction separated into facts, assumptions, and open questions
- The source's authority identified or marked for confirmation
- Every plausible contract impact classified as confirmed or potential
- An interim work posture selected
- A neutral confirmation email reviewed for accidental acceptance
- A clear request for authorized written direction included
Sample
This is sample data, not your prompt. Pro unlocks this higher-stakes Playbook. On Free Playbooks you can still copy the assembled prompt into any AI.
Sample input
Contract context: Task Order 4 covers weekday system testing in the approved environment. No weekend testing or second environment is listed. Direction: During the September 22 status call, the agency program manager said to start weekend testing in a second environment next week and "sort out the paperwork later." Authority: The speaker isn't identified as the contracting officer and has no known authority to change scope. Impact: Possible weekend labor, environment setup, security coordination, and disruption to the current test sequence. Estimates aren't validated. Current posture: No added work started. Urgency: Within 24 hours. Desired response: Written contracting officer confirmation by noon tomorrow, after review by the contracts manager and program director.
Sample assembled prompt
Subject: Confirmation Requested - Weekend Testing... Our current understanding is that this... We are reviewing the potential effect... Those impacts aren't yet validated. Pending written confirmation from an authorized... Please confirm by noon on September... We remain ready to coordinate quickly... Nothing in this message is intended... Regards, Contract Program Lead