Move a Change From Request to Approval

Made for General Contractors

Move a Change From Request to Approval

90 min Advanced General Contractor Improve Operations Career outcome: Avoid Professional Risk

Route an owner request or field condition through impact review, written approval, crew release, and project record updates.

Create a free account to save your progress and use this Playbook.

Use this when

An owner requests different work, a concealed condition changes the plan, or a design revision affects cost, time, or trade coordination.

You'll need

  • Change summary
  • Request source
  • Contract route
  • Current work status
  • Relevant contract terms
  • Scope evidence
  • Cost details
  • Schedule details
  • Approval authority
  • Required response date
  • Relationship concerns

You'll get

  • The change source and changed scope documented
  • Contract notice and authorization requirements checked
  • Cost support and credits reconciled
  • Schedule effects tied to affected activities
  • Assumptions, exclusions, and open items stated
  • Written approval or contract-based direction recorded

By the end of this playbook

You will have:

  • The change source and changed scope documented
  • Contract notice and authorization requirements checked
  • Cost support and credits reconciled
  • Schedule effects tied to affected activities
  • Assumptions, exclusions, and open items stated
  • Written approval or contract-based direction recorded

Sample

This is sample data, not your prompt. Pro unlocks this higher-stakes Playbook. On Free Playbooks you can still copy the assembled prompt into any AI.

Sample input

Change summary: The owner requested taller storefront doors after framing was complete.
Request source: Owner request
Contract route: Change order before work
Current work status: Affected work paused
Relevant contract terms: Written owner approval is required before changed work. Itemized backup and schedule impact are required.
Scope evidence: Issued detail A8.3, owner email, RFI 27, revised sketch SK-14, and field photos.
Cost details: Door subcontractor quote of $8,600, estimated framing rework of 24 labor hours, and original material credit pending.
Schedule details: Six-week fabrication lead time. Storefront close-in and final inspection may move by ten workdays.
Approval authority: Owner signs the change. Project executive approves internal exposure. Superintendent receives the field release.
Required response date: October 2 to preserve the fabrication slot.
Relationship concerns: The owner views the request as a small substitution and may dispute rework costs.

Sample assembled prompt

CHANGE STATUS Recommended route: Hold changed...
Decision deadline: October 2.
Reason: The contract requires approval before...
SCOPE DIFFERENCE Original: Storefront doors shown...
Revised: Taller doors shown on SK-14.
Added work: Revised fabrication, framing rework,...
Open point: Confirm whether hardware or...
PRICE REVIEW Supported: $8,600 subcontractor quote.
Pending: Original material credit, framing labor...
Risk flag: Don't present a...
SCHEDULE REVIEW Known constraint: Six-week fabrication...
Potential impact: Ten workdays to storefront...
Required proof: Updated activity path, available...
OWNER DECISION Option 1: Approve by...
Option 2: Keep the specified doors...
Option 3: Approve design work now...
WORK GATE No revised door release...