Manage a Client Change After Construction Starts

Made for Architects

Manage a Client Change After Construction Starts

Also useful for: Project Managers, people in Creative

120 min Advanced Creative Architect Build Professional Skills Career outcome: Avoid Professional Risk

Take a client request from informal conversation to controlled construction action. You verify site facts, test options, document cost and schedule exposure, secure approval, and issue coordinated information.

Create a free account to save your progress and use this Playbook.

Use this when

Use this when your client requests a design or scope change after construction has started, especially when related work is already installed, ordered, fabricated, inspected, or scheduled.

You'll need

  • Change request
  • Reason and decision deadline
  • Construction status
  • Site conditions and completed work
  • Authority requirements
  • Affected project information
  • Contractor and consultant input
  • Cost and schedule information
  • Known options and constraints
  • Document history

You'll get

  • The requested change defined
  • The current approved baseline preserved
  • Affected site conditions verified, or a clear record of what remains unverified
  • Viable options compared
  • Cost and schedule exposure documented
  • Required approvals identified

By the end of this playbook

You will have:

  • The requested change defined
  • The current approved baseline preserved
  • Affected site conditions verified, or a clear record of what remains unverified
  • Viable options compared
  • Cost and schedule exposure documented
  • Required approvals identified

Sample

This is sample data, not your prompt. Pro unlocks this higher-stakes Playbook. On Free Playbooks you can still copy the assembled prompt into any AI.

Sample input

You receive a request to replace six swing doors with sliding doors on Level 3 of your healthcare project. Your contractor has started framing, approved doors are in fabrication, and the framing inspection is four business days away. You can request pricing, but your client must approve additional services and construction cost. You have preliminary warnings about lead time, access-control power, ceiling coordination, and possible rework, but you don't yet have firm quotations.

Sample assembled prompt

You get a change-control package that...
Your package identifies fabricated doors, framing,...
You compare the approved swing doors,...
You recommend checking the layout adjustment...
You also receive a decision brief,...

Part of a collection

Handle the Client Change Without Wrecking the Project

10 playbooks

Learn how to assess a proposed design change, clarify the request, compare realistic options, secure approvals, and document each decision before the project drifts.

Next: Prepare for a Tough Scope and Fee Conversation

View collection

Best next playbooks

Suggest an idea

What should we add?

Loading the suggestion form…