Price and Approve a Change Order

Made for Independent Contractors

Price and Approve a Change Order

Also useful for: people in Entrepreneurship

35 min Intermediate Business & Entrepreneurship Earn More

Document changed work, calculate the price and timeline impact, and send a clear approval request before taking on the extra work.

Create a free account to save your progress and use this Playbook.

Use this when

A client asks for added work, removes part of the job, changes a requirement, requests another revision, or causes a delay that affects your cost or schedule.

You'll need

  • Project details
  • Original scope
  • Requested change
  • Cost and time details
  • Pricing method
  • Schedule effect
  • Approval and payment terms

You'll get

  • Original and changed scope separated
  • Added and removed work documented
  • Net price adjustment calculated
  • Schedule effect stated
  • Exclusions and assumptions listed
  • Written approval request ready to send.

By the end of this playbook

You will have:

  • Original and changed scope separated
  • Added and removed work documented
  • Net price adjustment calculated
  • Schedule effect stated
  • Exclusions and assumptions listed
  • Written approval request ready to send.

Sample

This is sample data, not your prompt. Pro unlocks this higher-stakes Playbook. On Free Playbooks you can still copy the assembled prompt into any AI.

Sample input

Project: Three custom built-in shelving units for a residential client.
Original scope: Painted units with open shelves, standard pulls, one revision, delivery, and two installation days.
Change: Add doors to all units, upgrade to brass pulls, and remove one shelf.
Costs: 12 added labor hours at $65, $420 for doors, $180 for hardware, $95 for an extra visit, less $105 saved from the removed shelf.
Pricing method: Fixed price.
Schedule: Three added fabrication days and completion moved to May 19.
Terms: Approval by May 5, 50% deposit at approval, no changed work before payment.

Sample assembled prompt

CHANGE ORDER: Built-In Shelving Door and...
- Supply and install brass pulls.
- Complete one added site visit...
Removed work: - Remove one open...
Price adjustment: - Added labor: $780...
Final completion moves to May 19...
Approval: Changed work will begin after...

Part of a collection

Price the Work Without Regretting It Later

10 playbooks

Turn hours, materials, travel, overhead, changes, and risk into clear prices that cover the work and leave room for profit.

Next: Set Your Minimum Profitable Rate

View collection

Best next playbooks

View all related playbooks →
Suggest an idea

What should we add?

Loading the suggestion form…