Qualify and Award the Right Subcontractor

Made for General Contractors

Qualify and Award the Right Subcontractor

120 min Advanced Decisions Make a Decision Need to Compare Options

Level competing bids, verify coverage and capacity, resolve exceptions, and prepare a clear subcontract award record.

Create a free account to save your progress and use this Playbook.

Use this when

You have two or more subcontractor bids for the same trade and need to choose, negotiate with, and award the strongest option.

You'll need

  • Project and trade scope
  • Bid requirements
  • Bidder proposals
  • Schedule and capacity needs
  • Qualification requirements
  • Decision priorities
  • Commercial rules
  • Risk posture

You'll get

  • Every proposal checked for responsiveness
  • Every bid normalized to the same comparison basis
  • Every material scope gap assigned a severity and next action
  • Every capacity concern supported by evidence or marked for verification
  • Every pre-award blocker answered or carried into a written award condition
  • The award recommendation approved and documented

By the end of this playbook

You will have:

  • Every proposal checked for responsiveness
  • Every bid normalized to the same comparison basis
  • Every material scope gap assigned a severity and next action
  • Every capacity concern supported by evidence or marked for verification
  • Every pre-award blocker answered or carried into a written award condition
  • The award recommendation approved and documented

Sample

This is sample data, not your prompt. Pro unlocks this higher-stakes Playbook. On Free Playbooks you can still copy the assembled prompt into any AI.

Sample input

Project: Occupied office renovation
Trade: Electrical
Bidders: Atlas Electric at $412,000, Beacon Power at $398,000, and Current Systems at $427,500
Top priorities: Complete scope, reliable supervision, schedule, then total cost
Known concern: Beacon excludes temporary power and doesn't identify a dedicated foreperson. Atlas includes temporary power but lists fire alarm as excluded. Current includes the broadest scope but requests material escalation after 30 days.
Required start: May 6
Risk posture: Balanced

Sample assembled prompt

Preliminary recommendation: Conditional award to Atlas...
Leveled position: 1.
Atlas Electric: $412,000 submitted.
Temporary power included.
Fire alarm boundary unresolved.
2. Beacon Power: $398,000 submitted.
Temporary power excluded and supervision not...
Leveled total remains TBD until both...
3. Current Systems: $427,500 submitted.
Broadest stated coverage, but open-ended escalation...
Primary decision point: Beacon's $14,000 apparent...
Atlas currently offers the strongest balance...
Required award conditions: - Written scope...
- Named dedicated foreperson and staffing...
- Acknowledgment of all addenda.
- Acceptance or marked resolution of...
- Confirmation of required insurance and...
Backup position: Keep Beacon active through...
Don't release Atlas until every...